Sunday, February 2, 2020

Winter Project 2020 - Update


Four weeks into the job, in fact just the weekends we worked on the second bathroom, that's where we stand as of today. Cables and pipes are all in and next week we will connect the water. The following steps include the floor heating, the floor itself, tiles, bathtub, toilet etc. It's still a fair bit of work but we are on track. Our goal is to have the bathroom finished around spring time.